Work goes on, today we saw more plasterboard going up on the ceiling and all round the workshop, just cutting in to do. The electric cupboard, now formed, and a door liner made, should be ready for boarding. The first light cables for the workshop, table 1 and 2 are in place, ready to drop through the ceiling. The tea bar zone is all studed out, awaiting plasterboard and the power ring cables, for fridge, kettle, microwave, coffee machine etc. Nearly all the big holes in the walls have been bricked up and filled in.

So, tomorrow, it is on to the floor insulation and flooring next, more insulation and more plasterboarding. and continuing the boundary wall up to the eaves 6 metres up.